Upcoming Events

A Network Computing Webinar:
Avoiding Downtime: How Virtualization Can Help In Times of Trouble

June 12, 2013
11:00 AM PT / 2:00 PM ET

Are you caught between a desire for the benefits of the cloud and concerns about security and control? Then you should attend this insight-packed webinar to learn how private data networking technologies like MPLS IP-VPNs can address your concerns and allow you to safely and intelligently reap the savings, agility and other benefits associated with cloud computing.

Join us to hear top industry experts discuss the private data network technologies that are best suited for enterprise cloud access requirements. You won't want to miss this opportunity to learn how your organization can best mitigate risk while reaping the full potential benefits of the cloud.

Register Now!

More Events »

Subscribe to Newsletter

  • Keep up with all of the latest news and analysis on the fast-moving IT industry with Network Computing newsletters.
Sign Up

The Physical-to-Virtual Cookbook Part 1

Before embarking on any actual migration, you must understand the applications and physical devices you have in your data center. This is easier said than done for many organizations. You must understand the complete logical and physical application topology before you touch anything, especially complex, multitier applications.

We used a set of application dependency mapping tools at our client's site, including an appliance that was connected to the network. A network administrator configured port mirroring to the appliance to collect and store transaction data for us to examine. We used the OPNET Response Xpert appliance in conjunction with the OPNET appMapper Xpert application. (OPNET was recently acquired by Riverbed.)

More Insights

Webcasts

More >>

White Papers

More >>

Reports

More >>

We ran the appliance for about one week and collected interconnect information across 100 applications. In addition to server-to-server connectivity, the appliance also mapped details such application connections at the port level. This gave us a complete picture of the client's data center environment. We also discovered some custom applications that didn't show up in the client's software inventory spreadsheets.

With our dependency data in hand, we then needed performance metrics for the applications. This would allow us to accurately size the virtual servers that would be used in the migration. Our client already had the open-source Paessler PRTG Network Monitor installed. This tool collected CPU, memory, I/O throughput and disk statistics. Luckily, this tool had been running for 12 months, so we had a good baseline of metrics from which to draw.

This isn't the case with everyone; in many of our clients' environments we need to install agents on the applications to collect performance metrics, and then allow at least 30 to 45 days of data to capture baseline performance data. Agent installation can be time-consuming and expensive, particularly if you only plan to use agents during a migration, so consider open-source options like CACTI or Helios if you do not regularly monitor your application environment.

In a typical P2V migration you should analyze your existing hardware, but we were confident that the client's physical inventory was solid and that it had a good record of the type of hardware, CPU with socket count, core count, amount of memory and local storage. However, even with a detailed inventory and IP addresses for servers and applications, we still had to physically find these servers in the data center.

In addition to gathering technical details, we also decided to send out application questionnaires and conduct interviews with some of the key stakeholders to determine if there were areas for improvement. IT pros rightly focus on improving efficiency and lowering costs, but it's also important to check in with users to see if their service expectations are being met and find out if they are happy with the applications provided by IT.

We found the questionnaire to be an effective way to communicate with the client's key users about the migration and to verify the information we'd collected. We also discussed future growth plans and organizational needs that would increase load on the client's infrastructure, and looked into applications that were no longer supported or being phased out. The questionnaires and interviews also helped to bring people on board by making them part of the process, which is always good when interjecting change.

In Part 2 of this series, we'll delve more deeply into application dependency mapping and gathering performance metrics.

Don Magrogan is CTO of Fusion PPT, a cloud computing strategy and technology solution firm.


Page: « Previous Page | 1 2  


Related Reading


Network Computing encourages readers to engage in spirited, healthy debate, including taking us to task. However, Network Computing moderates all comments posted to our site, and reserves the right to modify or remove any content that it determines to be derogatory, offensive, inflammatory, vulgar, irrelevant/off-topic, racist or obvious marketing/SPAM. Network Computing further reserves the right to disable the profile of any commenter participating in said activities.

 
Disqus Tips To upload an avatar photo, first complete your Disqus profile. | Please read our commenting policy.
 